skip navigation

CSA REMODEL UPDATE

https://cdn2.sportngin.com/attachments/photo/4941-137053686/Heat_Reclaim_Tanks_thumb.JPG
  • North Wall

  • West Wall

  • South Wall Mezzanine

  • CYHA Storage

  • Hallway to Dryland/Weight Room

  • Locker Room Hallway West

  • Locker Room Hallway Entrance

  • Mezzanine

  • Locker Room Hallway East

  • East Wall

  • Lobby

  • Evaporative Condenser

  • Lobby Exterior

  • 5.29.19

    The sub-floor heat piping is completed. The sand to cover the piping is being hauled in today. Next week the insulation that covers the sub-floor will be installed. After that work on the refrigerant pipes will start
  • 5.28.19

    Mechanical piping trenches
  • 5.24.19

    The curb is 95% complete. Work on the Ice Plant and Tubing will begin soon.
  • 5.21.19

    Work continues on the curbing.
  • 5.21.19

  • 5.20.19

    Concrete is pumped in for the ice sheet curbing.
  • 5.20.19

  • 5.20.19

    Curbing for the outside of the ice sheet area is in poured.
  • 5.20.19

  • 5.15.19.

    New NHL size Rink is framed.
  • 5.15.19

  • 5.15.19

  • 4.16.19

    1. Bleachers, boards and glass are out. Work to remove the floor has begun.
  • 4.29.19

    2.
  • 4.29.19

    3.
  • 4.29.19

    4. Work continues to remove the concrete floor.
  • 5.3.19

    5. Concrete floor has been completely removed.

Loading…

CSA REMODEL UPDATE